3
|
6
|
Water quality: pool water pH |
No |
No
|
No |
pH 7.1. Maintain between 7.2 and 7.8. Corrected to 7.2. |
|
5
|
4
|
Water quality: daily written records of water quality and test kit kept on site |
No |
No
|
No |
Operator with better record keeping. Cyanuric Acid readings of 200ppm. Operator retested and got ~ 30ppm. Ensure proper water chemistry tests are done and recorded. |
|
16
|
4
|
Premises: fence or barrier with self-closing, self-latching gates properly constructed and maintained |
No |
No
|
No |
Fence 47" high at one corner where conduit was burried. Maintain fence at least 48" high w/ no gaps > 4" through the fence and no gaps > 2" under the fence. Corrected by operator, builder plans on removing conduit. |
|
17
|
4
|
Premises: decks unobstructed, properly drained, free of trip hazards |
No |
No
|
No |
One chair too close to pool. Maintain at least 8 feet deck clearance. Corrected. |
|
29
|
2
|
Dressing and sanitary facilities: required fixtures provided, clean, and in good repair |
No |
No
|
No |
Hot water ~ 120F. Maintain at 110F or less. Corrected by operator. |