3
|
6
|
Water quality: pool water pH |
No |
No
|
No |
.2535(1) Maintain pH at 7.2 to 7.8. Observed pH measuring 6.9 according to EHS test kit. CDI: CPO attempted to adjust pH and pH now measures 8.2. CPO stated he has no acid to lower the pH today. PERMIT DENIED. |
|
5
|
4
|
Water quality: daily written records of water quality and test kit kept on site |
No |
No
|
No |
.2535(10) Provide test kit capable of measuring disinfectant level, cyanuric acid and total alkalinity. Observed test kit with some testing chemicals expired. CDI: CPO ordered a new test kit while EHS was on site. |
|
6
|
6
|
Submerged suction outlets meet ASME/ANSI A112.19.8-2007. Single drains protected. (.2537, .2539) GPM= ____Field verification complete=____ |
No |
No
|
No |
.2539(b) All suction outlets shall be protected by anti-entrapment cover/grates in compliance with APSP-7. Observed vacuum line pulling suction with rubber boot like cap installed. CPO stated that he leaves the vacuum on so that the cap cannot be removed. CDI: Vacuum line was turned off and properly threaded vacuum line cover was installed. |
|
7
|
4
|
Pool maintenance: pool walls and floor kept clean, free of debris and in good repair |
No |
No
|
No |
.2537(14) Keep pool surface and pool floor free of debris. Observed light debris on pool floor. |
|
15
|
6
|
Premises: body hook and ring buoy with throw rope or lifeguard with rescue tube provided and properly located |
No |
No
|
No |
.2530(a) Provide ring buoy for rope 1.5 times the width of the pool or 50 ft whichever is less. Observed throw rope measuring 26 FT. Field book states that rope shall measure 27 FT. CDI: New rope installed on ring buoy measuring 27 FT. |
|
22
|
6
|
Premises: emergency telephone provided |
No |
No
|
No |
.2530(f) Emergency phone shall be accessible to all pool users. Observed emergency phone stored in what appears to be a fire extinguisher box with a plexiglass shield that needs to be removed to access emergency phone. CDI: CPO removed plexiglass shielding so that phone is now accessible. |